Pulaski County Courthouse

Pulaski County Courthouse, 2021
More detailed courthouse renovation plans and visuals were made available to the public and both county boards during a joint session meeting on Monday, April 10. Starting at the north side of the courthouse, lead architect Matt Ireton said they plan on keeping parking the same, but are addressing...
The courthouse renovation project is slowly taking some steps forward. The Pulaski County Commissioners were advised at a regular meeting on Jan.17 that office space assignments and furniture selections are turning the corner. Pulaski County Community Development Commission Executive Director...
Although there is a clearer, firmer timeline for the courthouse renovation project, construction is not going to move forward as quickly as hoped. As the schedule stands now, the second round of drawings are expected to be ready in the middle of January. Then, budget updates based off of those...
Approximate cost estimates for the courthouse renovation project were revealed at a recent joint county council and commissioners meeting on Oct. 10. Since Tonn and Blank Construction received the specifications for the schematic design, they were able to submit updated cost estimates. The...
The various ongoing construction projects in the county are moving along, with plans and designs reaching some of their final stages. One of the most significant updates was on the highly anticipated courthouse project. Origer said that Tonn and Blank is currently reviewing the schematic design...
Discussions about vacating the East Annex offices, as well as potentially remodeling the West Annex, recently took place at a joint county council and commissioners meeting on Monday, Aug. 8. Pulaski County Community Development Commission Executive Director Nathan Origer said that one of the goals...
According to a new timeline, it is expected that the new year will usher in the start of the anticipated courthouse renovation construction project. The original start date was expected to be in November of this year, but due to some delays, it will likely be in January. Community development...
Both the courthouse project and the work release program are continuing to inch forward, but are still in the early stages of development. Currently, the courthouse project is progressing through the design phase, with two drafts of floor plans being presented to both boards. The two potential...
The Pulaski County Commissioners unanimously decided to enter into a contract with Tonn and Blank Construction Monday night, formally committing to moving the courthouse project forward. Once signed, the contract officially hires Tonn and Blank as the county's construction company to oversee and...
The county council and auditor are reviewing an ordinance that set the guidelines for obtaining a bond for the justice center phase of the courthouse renovation project.  According to the ordinance, the county would be obtaining a bond not to exceed $5,575,000. That bond is only for the work at the...